X. OBLIGATIONS OF THE CONCESSIONAIRE
X.1 The Concessionaire shall at its own cost and expense observe, undertake, comply
with and perform, in addition to and not in derogation of its obligations elsewhere setout
in this Agreement, the following:
make, or cause to be made, necessary applications to the relevant Governmental Agencies
with such particulars and details, as may be necessary for obtaining all Applicable
Permits, and obtain such Applicable Permits in conformity with the Applicable Laws;
notify to NHAI forthwith the occurrence of Financial Close;
Submit to NHAI certified true copies of each of the Project Agreements within 7 (seven)
days of their execution
Not make any replacement amendment or modifications to any of the Project Agreements
without the prior written consent of NHAI, and where such amendment or modification is
made without such consent, not to enforce such amendment or modification nor permit
enforcement thereof against NHAI in any manner whatsoever;
give NHAI not less than 30 (thirty) days prior notice entering into, amending or
replacing any Project Agreement so as to enable NHAI to provide its consent or offer its
comments, if any thereon.
remove promptly according to Good Industry Practice from the Project Highway all
surplus construction machinery and materials, waste materials (including, without
limitation, hazardous materials and waster water), rubbish and other debris (including
without limitation accident debris) and shall keep the Site in a neat and clean condition
and in conformity with the Applicable Laws and Applicable Permits;
procure, as required, the appropriate proprietary rights, licenses, agreements and
permissions for materials, methods, processes and systems used or incorporated into the
Project Highway;
provide all assistance to the independent Consultants as it may require for the
performance of its duties and services;

provide to NHAI reports on regular basis during the Construction Period and the
Operation Period in the form and manner set forth in this Agreement.
obtain and maintain in force on and from the Appointed Date all insurance in accordance
with the provisions of this Agreement and Good Industry Practice;
acquire such real estate, as the Concessionaire may deem appropriate for the Additional
Facilities and to indemnify and save harmless and defend GOI, NHAI, and STG from and
against all proceedings, claims, demands, cost, expense, loss and damage arising out of or
relating to the securing of rights to use such real estate by the Concessionaire or any
person claiming through or under the Concessionaire;
undertake Debt Service Payments in accordance with the Financing Documents;
levy and collect Fees from users of the Project Highway at the rates set forth in the
Notification and in accordance with this Agreement and regulate the traffic on the Project
Highway in accordance with the Applicable Laws;
ensure and procure that each Project Agreement contains provisions that entitle NHAI to
step into such agreement in its discretion in place and substitution of the Concessionaire
in the event of Termination of this Agreement on account of default or breach by the
Concessionaire;
appoint, supervise, monitor and control the activities of such Contractors under their
respective Project Agreements as may be necessary;
make reasonable efforts to maintain harmony and good industrial relations among the
personnel employed in connection with the performance of the Concessionaires
obligations under this Agreement;
comply with all Applicable Permits and Applicable Laws in the performance of the
Concessionaires obligations under this Agreement including those being performed by
any of the Contractors;

develop, implement and administer a surveillance and safety program for the Project
Highway and the users thereof and the Contractors personnel engaged in the provision of
any services under any of the Project Agreements including correction of, safety
violations and deficiencies, and taking of all other actions necessary to provide a safe
environment in accordance with Applicable Laws and good industry practice;
take all reasonable precautions for the prevention of accidents on or about the Project
Highway and provide all reasonable assistance and emergency medical aid to accident
victims;
not to place or create and nor permit any Contractor or other person claiming through
or under the Concessionaire to create or place any Encumbrance or security interest over
all or any part of site or the Project Assets, or on any rights of the Concessionaire
therein or under this Agreement, save and except as expressly set forth in this Agreement;
make its own arrangements for quarrying, and observe and fulfill the environmental and
other requirements under the Applicable Laws and Applicable Permits at
Concessionaires own cost and expense;
be responsible for safety, soundness and durability of the Project Highway including
ROB and other structures forming part thereof and their compliance with the Specifications
and Standards;
not claim or demand possession or control of any roads, structures or real estate which
do not form part of the Project Highway;
after receiving possession of the Site or part thereof, ensure that such Site remains
free from all encroachments and take all steps necessary to remove encroachments, if any
make payment to Police Department or any Government Agency, if required, for provision
of such services as are not provided in the normal course or are available on payment;
indemnify the NHAI against all actions, suits, claims, demands and proceedings and any
loss or damage or cost or expense that may be suffered by them on account of anything done
or omitted to be done by the Concessionaire in connection with the performance of its
obligations under this Agreement; and
comply with the Divestment Requirements and hand over the Project Highway to NHAI upon
Termination of the Agreement.

X.2 Subject to the terms and conditions of this Agreement the Concessionaire shall at
its cost and expense:
undertake the design, engineering, procurement and construction and financing of the
Project Highway in accordance with this Agreement;
operate and maintain the Project Highway at all times in conformity with this Agreement
including but not limited to the Specifications and Standards set forth in Schedule
D, the Maintenance Programme and Good Industry Practice.
X.3 The Concessionaire shall, before commencement of construction of the Project
Highway:
submit to NHAI with due regard to Project Completion Schedule as set forth in Schedule
H and Scheduled Project Completion Date, its design, engineering and
construction time schedule and shall formulate and provide CPM/PERT charts for the
completion of the said activities;
finalise the design and detailed engineering basis;
have requisite organisation and designate and appoint a Project Manager and such other
managers, officers and representatives as it may deem appropriate to supervise the Project
and to deal with the NHAI Representative and be responsible for all necessary exchanges of
information required pursuant to this Agreement; an
undertake, do and perform such acts, deeds and things as may be necessary or required
for construction and Project Completion under and in accordance with this Agreement.

X.4 In respect of the Concessionaires obligations with respect to the Drawings of
the Project Highway as set forth in Schedule I, the following shall apply:
The Concessionaire shall prepare and submit with reasonable promptness and in such
sequence as is consistent with the Project Completion Schedule, three copies each of all
Drawings to NHAI and the Independent Consultant for review and comments.
By forwarding the Drawings for review and comment to NHAI, the Concessionaire
represents that it has determined and verified that the design and engineering including
field construction criteria related thereto is in conformity with the Specifications,
Standards and quality set forth in this Agreement for and in respect of the Project
Highway.
Within 30 (thirty) days of the receipt of the Drawings, NHAI shall review the same and
convey its/their comments/observations to the Concessionaire with particular reference to
the conformity or otherwise with the Specifications and Standards set forth in this
Agreement. It is expressly agreed that notwithstanding any review and comment/observations
of NHAI on any Drawings or failure of NHAI to provide comments/ observations thereon. NHAI
shall not be liable for the same in any manner whatsoever and the Concessionaire shall
remain solely responsible for and shall not be relieved or absolved in any manner
whatsoever of its obligations, duties and liabilities as set forth in this Agreement. The
Concessionaire shall not be obliged to await the comments/observations of NHAI on the
Drawings submitted pursuant hereto beyond the period set forth hereinabove.

If the comments/observations of NHAI indicate that the Drawings are not in conformity
with the Specifications and Standards set forth in this Agreement such Drawings shall be
revised by the Concessionaire to the extent necessary and resubmitted to NHAI for review,
observations and comments. NHAI shall give its observations and comments, if any, within
15 (fifteen) days of the receipt of such revised Drawings provided, however, that any
observations or comments of NHAI or failure of NHAI to give any observations or comments
on such revised drawings shall not relieve or absolve the Concessionaire of its obligation
to conform to such Specifications and Standards
The Concessionaire shall be responsible for delays in Project Completion Schedule
caused by reasons of any Drawings not being in conformity with the Specifications and
Standards, and the Concession Period shall not be extended in any manner whatsoever on
account of submission or revision of any Drawings.
Within 90 (ninety) days of the COD, the Concessionaire shall furnish to NHAI with
"as built" Drawings reflecting the Project Highway as actually designed,
engineered and constructed, including without limitation an "as built" survey
illustrating the layout of the Project Highway and setback lines, if any, of the buildings
and structures forming part of Project Facilities.
X.5 The Concessionaire shall submit to NHAI the drafts of the Project Agreements
including in particular the EPC Contract, the O&M Contract and the Tolling Contract
for its review . NHAI shall have the right but not the obligation to provide its comments
and observations, if any, in respect of the Project Agreement within 30 (thirty) days of
the receipt thereof by NHAI and the Concessionaire shall consider all such
comments/observations. Any such comments/observations by NHAI on any Project Agreements or
the failure to provide such comments shall not relieve or absolve in any manner whatsoever
the Concessionaire of its obligations, duties and liabilities under this Agreement nor
shall it make NHAI and/or Independent Consultants liable to the Concessionaire in any
manner whatsoever and shall be without prejudice to the rights of NHAI hereunder.
X.6 During the Construction Period, the Concessionaire shall be responsible for
maintaining the Site including the existing two lanes of the Project Highway at its own
cost and expense in a manner that the level of service is at no time inferior to the level
prevailing immediately before the Appointed Date and at least 2 (two) lanes of the Project
Highway are ordinarily open to traffic at all times. The Concessionaire shall promptly
undertake all such repairs and maintenance works as may be necessary to keep the Project
Highway traffic-worthy and safe during the Construction Period.
X.7 The Concessionaire shall, at all times, afford access to the Site to the authorised
representatives of NHAI, Senior Lenders, and the Independent Consultant and to the persons
duly authorised by any Governmental Agency having jurisdiction over the Project, including
those concerned with safety, security or environmental protection to inspect the Project
Highway and to investigate any matter within their authority and upon reasonable notice,
the Concessionaire shall provide to such persons reasonable assistance necessary to carry
out their respective duties and functions with minimum disruption to the construction
operation and maintenance of the Project Highway consistent with the purpose for which
such persons have gained such access to the Site.

XI. OBLIGATIONS OF NHAI
XI.1 NHAI agrees to observe, comply and perform the following:
enable access to the Site, free from Encumbrances, in accordance with this Agreement;
peaceful use of the Site by the Concessionaire as licensee under and in accordance with
the provisions of this Agreement without any let or hindrance from NHAI or persons
claiming through or under it;
assist and provide all reasonable support to the Concessionaire in obtaining Applicable
Permits;
upon written request from the Concessionaire, assist the Concessionaire in obtaining
access to all necessary infrastructure facilities and utilities, including water,
electricity and telecommunication facilities at rates and on terms no less favourable to
the Concessionaire than those generally available to commercial customers receiving
substantially equivalent services;
procure that no barriers are erected or placed by STG or any Governmental Agency for
octroi, sales tax, and police checks on the Project Highway except on account of any law
and order situation or upon national security considerations;
assist the Concessionaire in entering into the State Support Agreement with STG;
assist the Concessionaire in obtaining necessary authority to regulate traffic on the
Project Highway subject to and in accordance with the Applicable Laws;
assist the Concessionaire in obtaining Police assistance from STG against payment of
prescribed costs and charges, if any, for traffic regulation, patrolling and provision of
security on the Project Highway;
operate and maintain the Project Highway during the Development Period, at its own cost
and expense, in a manner that the level of service is at no time inferior to the level
prevailing on the date when bids were received for this Concession; and
Observe and comply with its obligations set forth in this Agreement.

XII. REPRESENTATIONS AND WARRANTIES
XII.1 Representations and Warranties of the Concessionaire
The Concessionaire represents and warrants to NHAI that:
It is duly organized, validly existing and in good standing under the laws of the
jurisdiction of its incorporation;
It has full power and authority to execute, deliver and perform its obligations under
this Agreement and to carry out the transactions contemplated hereby;
It has taken all necessary corporate and other action under Applicable Laws and its
constitutional documents to authorize the execution, delivery and performance of this
Agreement;
It has the financial standing and capacity to undertake the Project;
This Agreement constitutes its legal, valid and binding obligation enforceable against
it in accordance with the terms hereof;
It is subject to civil and commercial laws of India with respect to this Agreement and
it hereby expressly and irrevocably waives any immunity in any jurisdiction in respect
thereof;
All the information furnished in the Bid is, and shall be, true and correct as on the
Appointed Day and COD and the Balance Sheet and Profit and Loss Account of the
Concessionaire for each of its Accounting Years after the Appointed Date furnished to NHAI
shall give true and fair view of the affairs of the Concessionaire.

It shall furnish a copy of the audited accounts of the Company within 120 (one hundred
twenty) days of the close of its each Accounting Year after the Appointed Date and any
material change subsequent to the date of such accounts shall be notified to NHAI by the
Concessionaire within 30 (thirty) days of its occurrence and warrants that the accounts
and the information furnished as aforesaid shall be true and correct;
The execution, delivery and performance of this Agreement will not conflict with,
result in the breach of, constitute a default under or accelerate performance required by
any of the terms of the Concessionaires Memorandum and Articles of Association or
any member of the Consortium or any Applicable Laws or any covenant, agreement,
understanding, decree or order to which it a party r by which it or any of its properties
or assets is bound or affected;
There are no actions, suits, proceedings, or investigations pending or, to the
Concessionaires knowledge, threatened against it at law or in equity before any
court or before any other judicial, quasi judicial or other authority, the outcome of
which may result in the breach of or constitute a default of the Concessionaire under this
Agreement or which individually or in the aggregate may result in any Material Adverse
Effect on its business, properties or assets or its condition, financial or otherwise, or
in any impairment of its ability to perform its obligations and duties under this
Agreement;

It has no knowledge of any violation or default with respect to any order, writ,
injunction or any decree of any court or any legally binding order of any Governmental
Agency which may result in any material adverse effect or impairment of the
Concessionaires ability to perform its obligations and duties under this Agreement;
It has complied with all Applicable Laws and has not been subject to any fines,
penalties, injunctive relief or any other Civil or criminal liabilities which in the
aggregate have or may have material adverse effect on its financial condition or its
ability to perform its obligations and duties under this Agreement;
The aggregate equity share holding of the Consortium Members and their Associates in
the issued and paid up equity share capital of the Concessionaire shall not be less than
(a) 51% (fifty one percent) during the construction period and for 5 (five) years
following COD, and (b) 26% (twenty six per cent) during the balance remaining Operations
Period;
Each Consortium Member was and is duly organised and existing under the laws of the
jurisdiction of its incorporation and has full power and authority to consent to and has
validity consented to and requested NHAI to enter into this Agreement with the
Concessionaire pursuant to the LOA and has agreed to and unconditionally accepted the
terms and conditions set forth in this Agreement;
All rights and interests of the Concessionaire in and to the Project Highway shall pass
to and vest in NHAI on the Termination Date free and clear of all liens, claims, and
Encumbrances without any further act or deed on the part of the Concessionaire or NHAI and
that none of Project Assets including materials, supplies or equipment forming part
thereof shall be acquired by the Concessionaire subject to any agreement under which a
security interest or other lien or Encumbrance is retained by any person save and except
as expressly provided in this Agreement;
No representation or warranty by the Concessionaire contained herein or in any other
document furnished by it to NHAI, or to any Governmental Agency in relation to Applicable
Permits contains or will contain any untrue statement of material fact or omits or will
omit to state a material fact necessary to make such representation or warranty not
misleading; and
It warrants that no sums, in cash or kind, have been paid or will be paid by or on
behalf of the Concessionaire, to any person by way of fees, commission or otherwise for
securing the Concession or entering into of this Agreement or for influencing or
attempting to influence any officer or employee of NHAI, GOI or STG in connection
therewith.

XII.2 Representations and Warranties of NHAI.
NHAI represents and warrants to the Concessionaire that:
NHAI is duly organised and validly existing under the laws of India;
NHAI has full power and authority to execute, deliver and perform its obligations under
this Agreement and to carry out the transactions contemplated hereby;
NHAI has taken all necessary action to authorise the execution, delivery and
performance of this Agreement;
This Agreement constitutes its legal, valid and binding obligation enforceable against
it in accordance with the terms hereof; and
NHAI is subject to civil and commercial laws of India with respect to this Agreement
and it hereby expressly and irrevocably waives any sovereign immunity in any jurisdiction
in regard to matters set forth in this Agreement.

XIII DISCLAIMER
13.1 The Concessionaire acknowledges that prior to the execution of this Agreement, the
Concessionaire has after a complete and careful examination made an independent evaluation
of the traffic volumes, Specifications and Standards, Site and all the information
provided by NHAI and has determined to the Concessionaires satisfaction the nature
and extent of such difficulties, risks and hazards as are likely to arise or may be faced
by the Concessionaire in the course of performance of its obligations hereunder.
13.2
The Concessionaire acknowledges and hereby accepts the
risk of inadequacy, mistake or error in or relating to any of the matters set forth in
Clause 13.1 above and hereby confirms that NHAI shall not be liable for the same in any
manner whatsoever to the Concessionaire.