In
the event of Concessionaire being in material default of this Agreement and such default
is cured before Termination, the Concessionaire shall pay to NHAI as compensation, all
direct additional costs suffered or incurred by NHAI arising out of such material default
by the Concessionaire, in one lumpsum within 30 (thirty) days of receiving the demand or
at the Concessionaires option in 3 (three) equal semi-annual installments with
interest @ SBI PLR plus 2% (two per cent).
34.2 In the event of NHAI being in material default of this Agreement and such default
is cured before Termination, NHAI shall pay to the Concessionaire as compensation, all
direct additional costs suffered or incurred by the Concessionaire arising out of such
material default by NHAI, in one lumpsum within 30 (thirty) days of receiving the demand
or at NHAIs option in 3 (three) equal semi-annual installments with interest @ SBI
PLR plus 2% (two per cent).

XXXV TERMINATION
35.1 Termination for the Concessionaire Event of Default.
35.1.1 Concessionaire Events of Default
The Following events shall constitute an event of default by the Concessionaire (a
"Concessionaire Event of Default") unless such Concessionaire Event of Default
has occurred as a result of NHAI Event of Default or a Force Majeure Event;
The Concessionaire fails to achieve Financial Close in accordance with the provisions
of Article XXIV;
The Concessionaire fails to achieve the Project Completion Schedule or any Project
milestone within the period set forth in Schedule H and fails to cure such
default within a period of 180 (one hundred and eighty) days from the date of its
occurrence.
The Concessionaire is in Material Breach of this Agreement;
The Concessionaire commits default in complying with any of the terms and conditions of
this Agreement, save and except those defaults in respect of which Cure Period has been
expressly provided in this Agreement, and fails to remedy or rectify the same upon receipt
of a notice in this behalf from NHAI which shall:
(i) require the Concessionaire to remedy the breach or breaches referred to in such notice
within 1 (one) month (or such longer period as may be agreed by the NHAI at its absolute
discretion); or
(ii) permit the Concessionaire to put forward within 15 days of such notice a reasonable
programme for the remedying of the breach or breaches, such programme to specify in
reasonable detail the manner in which such breach or breaches is or are proposed to be
remedied and the latest date by which it is proposed that such breach or all such breaches
shall be remedied.

The Concessionaire creates any Encumbrance, charges or lien in favour of any person
save and except as otherwise expressly permitted under Clause 38.2;
The shareholding of the Consortium Members falls below the minimum prescribed under
Clause 12.1 (xii) and the Concessionaire does not suo moto cure such default within 90
(ninety) days of its occurrence;
The transfer, pursuant to law of either (a) the rights and/or obligations of the
Concessionaire under any of the Project Agreements, or (b) all or material part of the
assets or undertaking of the Concessionaire except where such transfer in the reasonable
opinion of NHAI does not affect the ability of the Concessionaire to perform, and the
Concessionaire has the financial and technical capability to perform, its material
obligations under the Project Agreements;
a resolution is passed by the shareholders of the Concessionaire for the voluntary
winding up of the Concessionaire;
The Concessionaire is adjudged bankrupt or insolvent or if a trustee or receiver is
appointed for the Concessionaire or for any of its property that has a material bearing on
the Project;
Any petition for winding up of the Concessionaire is admitted by a court of competent
jurisdiction or the Concessionaire is ordered to be wound up by Court except for the
purpose of amalgamation or reconstruction provided that, as part of such amalgamation or
reconstruction, the property, assets and undertaking of the Concessionaire are transferred
to the amalgamated or reconstructed entity and that the amalgamated or reconstructed
entity has unconditionally assumed the obligations of the Concessionaire under this
Agreement and the Project Agreements, and provided that:
(i) the amalgamated or reconstructed entity has the technical capability and operating
experience necessary for the performance of its obligations under this Agreement and the
Project Agreements;
(ii) the amalgamated or reconstructed entity has the financial standing to perform its
obligations under this Agreement and the Project Agreements and has a credit worthiness at
least as good as that of the Concessionaire as at the Financial Close; and
(iii) each of the Project Agreements remains in full force and effect;
The Concessionaire is in material breach of any of the Project Agreements;
An event of default of the Concessionaire under any of the Financing Documents has
occurred or any of the Senior Lenders has recalled its loan under any of the Financing
Documents;

The Concessionaire abandons the operations of the Project Highway for more than 15
(fifteen) consecutive days without the prior consent of NHAI, provided that the
Concessionaire shall be deemed not to have abandoned such operation if such abandonment
was (i) as a result of Force Majeure Event and is only for the period such Force Majeure
is continuing, or (ii) is on account of a breach of its obligations by NHAI.
The Concessionaire repudiates this Agreement or otherwise evidences an intention not to
be bound by this Agreement;
The Concessionaire suffers an execution being levied on any of its assets/ equipment
causing a Material Adverse Affect on the Project and allows it to be continued for a
period of 15 (fifteen) days;
The Concessionaire has delayed any payment that has fallen due under this Agreement if
such delay exceeds 90 (ninety) days;
The Concessionaire is in breach of its obligation to repay the Revenue Shortfall Loans
in accordance this Agreement; or
The Concessionaire is in breach of its Six-Laning obligation under Article VIII of this
Agreement.
35.1.2 Save and except as otherwise provided in Clause 35.2, and without prejudice to
any other right or remedy which NHAI may have in respect thereof under this Agreement,
upon the occurrence of any breach or default by the Concessionaire under this Agreement
including any Concessionaire Event of Default, NHAI shall be entitled to terminate this
Agreement by a communication in writing (the "Termination Notice") to the
Concessionaire if the Concessionaire has failed to cure such breach or default within the
period provided for the same in this Agreement provided that before issuing the
Termination Notice, NHAI shall by a notice in writing inform the Concessionaire of its
intention to issue the Termination Notice (the "Preliminary Notice") and grant
15 (fifteen) days time to the Concessionaire to make its representation, if any, against
such intended Termination Notice and shall after the expiry of said 15 (fifteen) day
period whether or not it is in receipt of such representation, in its sole discretion
issue the Termination Notice.

35.1.3 Subject to Clause 35.2, the following shall apply in respect of cure of any of
the defaults and/or breaches of this Agreement.
The Cure Period shall commence from the date on which a notice in writing is delivered
by NHAI to the Concessionaire asking the latter to cure the breach or default specified in
such notice.
The Cure Period provided in this Agreement shall not relieve the Concessionaire from
liability for Damages caused by its breach or default;
The Cure Period shall not in any way be extended by any period of suspension under this
Agreement;
If the cure of any breach by the Concessionaire requires any reasonable action by
Concessionaire that must be approved by NHAI or the Independent Consultants hereunder the
applicable Cure Period (and any liability of the Concessionaire for damages incurred)
shall be extended by the period taken by NHAI or the Independent Consultants to accord
their required approval;
35.2 Notwithstanding anything to the contrary contained in this Agreement, in the event
of the Concessionaire being in default under any of the provisions hereof expressly
providing for Termination under or in accordance with this Clause 35.2, NHAI shall be
entitled to terminate this Agreement forthwith by issuing a Termination Notice to the
Concessionaire and upon issue of such Termination Notice by NHAI this Agreement shall
stand terminated forthwith. Provided, however, that prior to such Termination, NHAI shall
by notice grant to the Concessionaire a Cure Period of one month for curing the relevant
breach or default of the provisions of this Agreement.
35.3 Upon Termination by NHAI on account of occurrence of Concessionaire Event of
Default during the Operations Period, the NHAI shall pay to the Concessionaire by way of
Termination Payment an amount equal to 90% (ninety per cent) of the Debt Due and 90% of
Subordinated Debt less insurance claims, if any, Provided, however, that if all or any of
the insurance claims are not admitted and paid, then 80% (eighty per cent) of such unpaid
claims shall qualify for being included in the computation of Debt Due and Subordinated
Debt Due.

35.4 Termination for NHAI Events of Default.
35.4.1 The Concessionaire may after giving 90 (ninety) days notice in writing to NHAI
terminate this Agreement upon the occurrence and continuation of any of the following
events (each a "NHAI Event of Default"), unless any such NHAI Event of Default
has occurred as a result of Concessionaire Event of Default or due to a Force Majeure
Event.
NHAI is in breach of this Agreement and such breach has a Material Adverse Affect on
the Concessionaire and NHAI has failed to cure such breach or take effective steps for
curing such breach within 90 (ninety) days of receipt of notice in this behalf from the
Concessionaire;
NHAI repudiates this Agreement or otherwise evidences an irrevocable intention not to
be bound by this Agreement;
NHAI has delayed any payment that has fallen due under this Agreement if such delay
exceeds 90 (ninety) days.
35.4.2 Upon Termination by the Concessionaire on account of an NHAI Event of Default,
the Concessionaire shall be entitled to receive from NHAI by way of Termination Payment a
sum equal to:
the total Debt due, plus
the total Subordinated Debt Due, plus
150% (one hundred fifty per cent) of the Equity (subscribed in cash and actually spent
on the Project but excluding the amount of Equity Support referred to in Article XXV) the
if such Termination occurs at any time during three years commencing from the Appointed
Date and for each successive year thereafter, such amount shall be adjusted every year to
fully reflect the changes in WPI during such year and the adjusted amount so arrived at
shall be reduced every year by 7.5% (seven and a half per cent) per annum.

35.5 Upon Termination of this Agreement for any reason whatsoever, NHAI shall:
(i) take possession and control of Project Highway forthwith;
(ii) take possession and control forthwith of any materials, construction plant,
implements, stores etc. on or about the Site;
restrain the Concessionaire and any person claiming through or under the Concessionaire
from entering upon the Site or any part of the Project Highway; and/or
succeed upon election by NHAI without the necessity of any further action by the
Concessionaire, to the interests of the Concessionaire under such of the Project Agreement
as NHAI may in its discretion deem appropriate and shall upon such election be required to
compensate such contractors only for compensation accruing and becoming due and payable to
them under the terms of their respective Project Agreements from and after the date NHAI
elects to succeed to the interests of the Concessionaire as aforesaid. All sums claimed by
such Contractors as being due and owing for work and services performed or accruing on
account of any act, omission or event prior to such date shall constitute debt between the
Concessionaire and such Contractors and NHAI shall in no way or manner be liable or
responsible for such sums.
35.6 Termination Payments: The Termination Payment pursuant to this Agreement shall
become due and payable to the Concessionaire by NHAI within thirty days of a demand being
made by the Concessionaire with the necessary particulars duly certified by the Statutory
Auditors. If NHAI fails to disburse the full Termination Payment within 30 (thirty) days,
the amount remaining unpaid shall be disbursed along with interest @ SBI PLR plus two per
cent for the period of delay on such amount.
35.7 Mode of Payment: Payment of compensation of costs by NHAI pursuant to this Article
XXXII shall be made by way of credit to the Escrow Account and such payment shall
constitute valid discharge of NHAIs obligations for Termination Payment hereunder.
35.8 Notwithstanding anything to the contrary contained in this Agreement, any
Termination pursuant to the provisions of this Agreement shall be without prejudice to
accrued rights of either Party including its right to claim and recover money damages and
other rights and remedies which it may have in law or contract. All rights and obligations
of either Party under this Agreement, including without limitation Termination Payments
and Divestment procedures, shall survive the Termination of this Agreement to the extent
such survival is necessary for giving effect to such rights and obligations.

XXXVI DIVESTMENT OF RIGHTS AND INTERESTS
36.1 Upon Termination of this Agreement, the Concessionaire shall comply with the
following:
notify to NHAI forthwith the location and particulars of all Project Assets; and
deliver forthwith actual or constructive possession of the Project Highway free and
clear of all Encumbrances and execute such deeds, writings and documents as may be
required by the NHAI for fully and effectively divesting the Concessionaire of all of the
rights, title and interest of the Concessionaire in the Project Highway; and
Comply with the Divestment Requirements set out in Clause 36.2.
36.2 Upon Termination of this Agreement, the Concessionaire shall comply and conform to
the following Divestment Requirements in respect of the Project Highway:
all Project Assets including the road, pavement, structure and equipment shall have
been renewed and cured of all defects and deficiencies as necessary so that the Project
Highway is compliant with the Specifications and Standards set forth in this Agreement;
all sections of each traffic lane (the "Carriageway") of the Project Highway
shall have a roughness index of not more than 2500 mm per km and shall be free from
defects in accordance with O&M requirements;
all lamps shall be in working condition;
The Concessionaire delivers relevant records and reports pertaining to the Project
Highway and its design, engineering, construction, operation, and maintenance including
all operation and maintenance records and programmes and manuals pertaining thereto and
complete as built Drawings on the Divestment Date;
The Concessionaire execute such deeds of conveyance, documents and other writings as
the NHAI may reasonably require to convey, divest and assign all the rights, title and
interest of the Concessionaire in the Project Highway free from all Encumbrances
absolutely unto the NHAI or its Nominee; and
The Concessionaire complies with all other requirements as may be prescribed under
Applicable Laws to complete the divestment and assignment of all the rights, title and
interest of the Concessionaire in the Project Highway free from all Encumbrances
absolutely to NHAI or its nominee.

36.3 Not earlier than 3 (three) months before the expiry of the Concession Period but
not later than 30 (thirty) days before such expiry, or in the event of earlier termination
of this Agreement, immediately upon but not later than 15 (fifteen) days from the date of
issue of Termination Notice, the Independent Consultant shall verify, in the presence of a
representative of the Concessionaire, compliance by the Concessionaire with the Divestment
Requirements set forth in Clause 36.2 in relation to the Project Highway and, if required,
cause appropriate tests to be carried out at the Concessionaires cost for
determining the compliance therewith. If any shortcomings in the Divestment Requirements
are found by either Party, it shall notify the other of the same and the Concessionaire
shall rectify the same at its cost. The provisions of Article XXXVII shall apply mutatis
mutandis in relation to repair or curing of defects under this Article XXXVI.
36.4 Upon the Concessionaire conforming to all Divestment Requirements and handing over
actual or constructive possession of the Project Highway to NHAI or a person nominated by
NHAI in this regard, NHAI shall issue a certificate substantially in the form set forth in
Schedule V (the "Vesting Certificate") which will have the effect of
constituting evidence of divestment of all rights, title and lien in the Project Highway
by the Concessionaire and their vesting in NHAI pursuant hereto. Issue of the Vesting
Certificate shall not be unreasonably withheld by NHAI. The divestment of all rights title
and lien in the Project Highway shall be deemed to be complete on the date when all the
Divestment Requirements have been fulfilled or the Vesting Certificate has been issued,
whichever is earlier, it being expressly agreed that any defect or deficiency in any
Divestment Requirement shall not in any manner be construed or interpreted as restricting
the exercise of any rights by NHAI or its nominee on or in respect of the Project Highway
on the footing as if all Divestment Requirements have been complied with by the
Concessionaire.
36.5 Notwithstanding anything to the contrary contained in this Agreement, any
Termination Payments made by NHAI into the Escrow Account shall not be withdrawn therefrom
for any purpose whatsoever until the Vesting Certificate has been issued by NHAI under
this Article. Provided, however, that the aforesaid restriction shall not apply to
withdrawals from the Escrow Account in favour of the Senior Lenders to the extent of Debt
Due.